This new page will cover any announcements, proceedings, etc. involved with the Mandate covered by our Township 537 Plan. The first project to be addressed is the Low Pressure Sewer System Extension coming to the area of Houck Manor and Holiday Park. As we move forward, we will have links and postings of press releases, drawings, etc. detailing the progress. The homepage of this site will always notify the public of new additions to this page.

 

 

4/9/2019

PROPOSED HOUCK MANOR CONSTRUCTION SCHEDULE

 

The following is the PROPOSED construction schedule for the installation of public sewer in Houck Manor. We ask that affected homeowners contact the Authority to discuss the lateral location that best suits them no later than JUNE 1st. If the Authority does not hear from a homeowner, the laterals will be placed as shown on the final design drawing of the sewer system as shown at the meeting on November 15th 2018. 

 

MID MAY - Project Begins With Mainline Installation On Hillside Road

 

JUNE 1 - LAST DAY TO PLACE LATERAL STAKES. IF A STAKE IS NOT PLACED BY AN AUTHORITY EMPLOYEE WITH THE HOMEOWNER'S DIRECTION, THE AUTHORITY WILL ASSUME THAT THE HOMEOWNER IS CONTENT WITH THE LOCATION OF THE LATERAL ON THE FINAL DESIGN DRAWING.

 

MID JUNE - Mainline Installation On Chestnut Avenue And Walnut Avenue

 

LATE JUNE - Lateral Installation Begins On Hillside Road

 

EARLY JULY - Lateral Installation On Chestnut Avenue And Walnut Avenue

 

THROUGHOUT JULY - Installing Air Releases And Cleanouts In The Mainline

 

MID JULY - Installation Of The Mainline On Linglestown Road

 

THROUGHOUT AUGUST - Lateral Installation on Linglestown Road

 

LATE AUGUST - Blacktop Patching and Lawn Repair

 

Grinder pump installation will begin in EARLY SEPTEMBER, once the system has been installed and tested.

 

 

 

 

GENERAL / PLUMBING CONTRACTOR LIST 2019
contractor list.pdf
Adobe Acrobat document [193.5 KB]
Reference Submittal for Houck Manor Simplex Grinder Stations
A submittal for the Simplex Grinder Stations that will be supplied to Houck Manor. This submittal is for refernce purposes regarding the installation and operation of the stations for use by the installer and homeowner.
Submittal West Hanover Houck Manor Simpl[...]
Adobe Acrobat document [8.3 MB]
Presentation for the November 15th, 2018 Meeting Regarding Holiday Park
The set of slides to be shown at the November 15th Informational Meeting for the Holiday Park Sewer Extension.
2018.11.15 Holiday Park Public Meeting -[...]
Adobe Acrobat document [4.5 MB]
Responses To Questions Raised at the 5.15.2018 Authority Meeting
Response to questions raised at the 5-15[...]
Adobe Acrobat document [108.2 KB]
Responses to the Questions Raised at the December 19th 2017 Authority Meeting
Responses to Questions from 12 19-17 Aut[...]
Adobe Acrobat document [393.1 KB]
Myers Grinder Pump Installations in PA
Myers Grinder Pump Installations in Cent[...]
Adobe Acrobat document [6.0 KB]
Responses to Residents' Questions at the November, 21st 2017 Regular Meeting
Click here to download a full list of the questions posed as well as the answers to each.
12-18-17 response to 11-21-17 questions.[...]